Three nested horizons: a 7-day sprint to ship the public demo, a 24-week plan to land MIT new University as the anchor tenant, and a multi-year commercial trajectory toward paying customers in 2029.
| Day | Milestone | Status |
|---|---|---|
| 1 | Variants boot + launcher; bug triage | done (partial) |
| 2 | Seed scripts fully implemented + bleed-through fix | pending |
| 3 | Compelling demo data per variant | pending |
| 4 | Landing page + topbar cross-variant switch | pending |
| 5 | Mac mini deploy + TLS + external URLs | pending |
| 6 | Module propagation verification (live test) | pending |
| 7 | Crawler pass + trust demo + buffer | pending |
Detail: FIRE_PLAN_RAVIKIRAN_DEMO_7D.md, Day-1 result: FIRE_PLAN_DAY1_REPORT.md (source in private repo).
Two parallel tracks. Each independent of the other for the first 8 weeks; merge in weeks 9-12 when the company starts to license CATALYST to MIT new University as its anchor tenant.
Full breakdown: PLAN.md (24 weeks, week-by-week, both tracks) — source in private repo.
Realistic dates from COMMERCIALIZATION_POLICY.md §5 (source in private repo). The 2-week cohort cadence (per feedback_cohort_cadence memory) is the operational data floor — actual production stability accumulates over the months that follow.
| Milestone | Realistic |
|---|---|
| Modularization refactor + spine gaps closed | 2026-09 |
| Ravikiran 2-week cohort exit | 2026-06 |
| R&D cohort exit | 2026-09 |
| MIT ADT R&D (first external) | 2027-04 |
| Full ERP functioning (≥6 portals × ≥2 tenants × 3mo) | 2028-03 |
| Software company incorporated (parallel) | 2027-12 |
| First three paying customer renewals | 2029-09 |
Weeks 1-12, ≤50 users
Mac mini co-located; second tenant alongside Ravikiran prod. Tailscale serve for internal.
Months 3-12, 50-500 users
India VPS — DigitalOcean Bangalore recommended for data residency. Postgres + gunicorn + nginx.
Year 2+, 1000+ across tenants
Per-tenant cloud — separate Postgres per tenant, per-tenant encryption keys.
Detail: HOSTING.md (source in private repo).
From PLAN.md §"Decisions blocking start of execution" (source in private repo):
Each is a 30-minute conversation. Until they're answered, the calendar above is precise but the dates are nominal.
Open-source ERPs to study and selectively borrow from: ERPNext (Frappe Education module), OpenEduCat (Odoo-based), Apache OFBiz, Tryton. Brief queued at docs/research/OSS_ERP_LANDSCAPE_BRIEF.md (source in private repo) for the next research-agent run.